Our New Track
(what else is new this spring)
(not too much was able to be done)
Macadem started.
(thank you)
Below are updated photos of what was done yesterday afternoon.
The High Jump pit had the first layer of black rubber placed.
The guys working on the ditch under the visitor's side bleachers for the wall.
Just the beginning stages of the retaining wall under visitor's bleachers.
The "Black" part of the track will be completed today.
We should start seeing "Stadium Blue" in the very near future!!!
The Wall underneath the visiting bleachers is coming along.
Senior Stand getting a fresh coat of paint.
The "Blue" you will see on the photos below is a sealant.
After the sealant gets put on...then the "Stadium Blue" track surface will be
getting placed. But we need NO RAIN at this point.
Current timeline based on SUNSHINE - which we have not been lucky with:
The rubber SHOULD be completed by next Friday, August 7
Then the painter will need two days to put the lines down for completion.
The track WILL BE a FULL 8 Lanes with each lane
being 42 inches wide (Maximum Standard).

As you can see from the above photos - today's weather is not good.
The hopes of continuing the sealant will take place tomorrow.
The guys are working on drying the track from the hard rains we had last night.
Also below is the continued work on improvements to the stadium.
Starting work today by drying off the track.
The staff is cutting down the hedges that line the fence by the football booster stand.
The continuing face lift of the home bleachers...the white cement is
being cleaned up with a fresh coat of gray paint.
Digging to do the wiring to the new scoreboard.
Lots of work gets done when the sun shines.
The method used to put the "Stadium Blue" on the track is amazing:
One guy sqweegies the polyurethane material on the area to be coated with the rubber pellets -
then others shovel the pellets onto the area where the poly was applied...
After the coating drys they will sweep off the pellets that did not stick.
The pellets are self-leveling...
Here's the first area of the track getting completed
(the runway took about 1/2 hour to complete):
It needs to "rain" blue pellets...
View from the road. (the lighter blue in the photo is a sealant used first)
The final coat of gray going on the grandstands today...
(looks great!)
They track guys anticipate getting all the runways and
the High Jump area completed today...then begin working on the track.
And yes, the track gets done the same way...
By shovel!
Working on the HJ area.
Pole Vault runway is complete.
The polyurethane getting ready...
The bleachers are done.
The sun is actually shining today!
Lots of rain this weekend.
Rained Friday into Saturday morning.
Spent most of day Saturday attempting to dry the track...then a brief shower
came on Saturday afternoon that halted the progress.
You can see on the track on the visitor's side - the difference in the blue sealant -
as to what was done over the weekend.
Heavy rains on Sunday.
This morning - prepping the track and taped off the inside.
This afternoon - the hopes are to have the track completely sealed.
Beginning the "Stadium Blue" pellets hopefully tomorrow on the track.
(that is a 3-4 day process).
Hopes for the track to be done by Friday - then the painter will arrive.
The blue you see on the track is the sealant.
The runway for the horizontal jumps is complete with the rubber.
Trying to give you a view of part of the wall underneath the bleachers.
AUG 3 - AFTERNOON PICTURES BELOW.
They put down a powder material to fill in any holes that may be present
before they put the liquid sealant down.
The machine used is like a zambony or a miniature street sweeper.
Emptying out the material.
Blowing off the pellets that did not stick to the polyurethane.
August 4, 2009 - AM Pictures
The sun is actually shining again today!
The start of the track...near the start/finish line.
The guys pour and spread the polyurethane just ahead of the guys shoveling on the track.
In an hour they had almost the first 25-30 M completed
The "Stadium Blue" pellets are emptied into the container ...
then emptied into the wheelbarrows.
August 4, 2009 - PM Pictures
The last section of powder and sealant is going down on the track.
Our bleachers with a fresh coat of paint
<SPA, N style="FONT-SIZE: 12pt">August 5, 2009 - AM Pictures
Threat of Thunderstorms today - making progress questionable
Started working on sealing the javelin runway.
Trim work is also being done around the inside of the track.
This morning they put the powder down (above)...
This afternoon the sealant was put down (below)...
If weather allows, they hope to complete the javelin area today.
Another part of the process I found out today...
The pellets come in 50 lb. bags. They break and dump the bags on the track
to loosen and break them up from the shipping process. And put them in the
BIG white sacks that were pictured above on an earlier date.
Edging the track.
Javelin area is complete minus the painting.
Views from near Band Booster Stand.
Edging the inside of the track too.
Cleaning off the pellets that did not stick.
Cleaning up the hedges that were in at the top of Stadium Hill.
Updated time line:
Hope to be completed with the track by Friday (weather pending)
Clean up and edge the track and other areas on Saturday.
Then the painter will arrive at some point after Saturday.
The painter will need approximately two-three days to paint the lines, etc.
Hopefully One week from today and the track will be completed.
Sod is going to be place on the field - hopefully next week.
The retaining wall located under visitor's bleachers -
hopefully completed next week.
August 6, 2009 - AM Pictures
Weather forecast looks pretty good for today and tomorrow.
The track surface should be completed tomorrow. Plan to get to the end of
the visitor's side - west end of the bleachers today.
The east end is near completion...working their way down the
straight-away of the visitor's side.
They hope to get completed down to the far light pole. Finish the remainder
on Friday.
Our staff is cleaning up the west end.
The edging has been completed on both the outside and inside of the track
on the home side.
The javelin area was edged this morning and is complete (minus painting).
August 6, 2009 - PM Pictures
THE END IS NEAR!
Only about 50 meters to go!
August 8, 2009
The blue is completed. Touch up work needs to be done on the last
50 meters that were done yesterday.
Painter arriving any day to paint the lines.
The only other item that needs to be done on the track after the painting...
an aluminum curb is being placed on the inside of the track.
IT IS ALMOST COMPLETED!
Close up view of the last part of the track that was completed yesterday.
August 10, 2009
The painter is getting all his marks set today and should be done tomorrow.
WOW!! The blue sees the paint!!
(completed July 30)
They are also painting all the concession stands white with blue trim.
(completed)
pole(s) at that end.
We all hope you love the improvements
Work still needs to be done...but we are making great strides.